• Skip to primary navigation
  • Skip to main content
  • Skip to primary sidebar
  • Skip to footer

Safety Risk .net

Humanising Safety and Embracing Real Risk

Discover More on this Site

  • Home
    • About
      • Privacy Policy
      • Contact
  • FREE RESOURCES
    • FREE SAFETY eBOOKS
    • FREE DOWNLOADS
    • TOP 50
    • FREE RISK ASSESSMENT FORMS
    • Find a Safety Consultant
    • Free Safety Program Documents
    • Psychology Of Safety
    • Safety Ideas That Work
    • HEALTH and SAFETY MANUALS
    • FREE SAFE WORK METHOD STATEMENT RESOURCES
    • Whats New In Safety
    • FUN SAFETY STUFF
    • Health and Safety Training
    • SAFETY COURSES
    • Safety Training Needs Analysis and Matrix
    • Top 20 Safety Books
    • This Toaster Is Hot
    • Free Covid-19 Toolbox Talks
    • Download Page – Please Be Patient With Larger Files…….
    • SAFETY IMAGES, Photos, Unsafe Pictures and Funny Fails
    • How to Calculate TRIFR, LTIFR and Other Health and Safety Indicators
    • Download Safety Moments from Human Resources Secretariat
  • PSYCHOLOGY OF SAFETY & RISK
    • Safety Psychology Terminology
    • Some Basics on Social Psychology & Risk
    • Understanding The Social Psychology of Risk – Prof Karl E. Weick
    • The Psychology of Leadership in Risk
    • Conducting a Psychology and Culture Safety Walk
    • The Psychology of Conversion – 20 Tips to get Started
    • Understanding The Social Psychology of Risk And Safety
    • Psychology and safety
    • The Psychology of Safety
    • Hot Toaster
    • TALKING RISK VIDEOS
    • WHAT IS SAFETY
    • THE HOT TOASTER
    • THE ZERO HARM DEBATE
    • SEMIOTICS
    • LEADERSHIP
  • Covid-19
    • COVID-19 (Coronavirus) Health and Safety Slogans and Quotes for the Workplace
    • Covid-19 Returning to Work Inductions, Transitioning, Safety Start Up and Re Entry Plans
    • Covid-19 Work from Home Safety Checklists and Risk Assessments
    • The Hierarchy of Control and Covid-19
    • Why Safety Loves Covid-19
    • Covid-19, Cricket and Lessons in Safety
    • The Covid-19 Lesson
    • Safety has this Covid-19 thing sorted
    • The Heart of Wisdom at Covid Time
    • How’s the Hot Desking Going Covid?
    • The Semiotics of COVID-19 and the Social Amplification of Risk
    • Working From Home Health and Safety Tips – Covid-19
    • Covid-19 and the Hierarchy of Control
  • Dr Rob Long Posts
    • Learning Styles Matter
    • There is no HIERARCHY of Controls
    • Scaffolding, Readiness and ZPD in Learning
    • What Can Safety Learn From Playschool?
    • Presentation Tips for Safety People
    • Dialogue Do’s and Don’ts
    • It’s Only a Symbol
    • Ten Cautions About Safety Checklists
    • Zero is Unethical
    • First Report on Zero Survey
    • There is No Objectivity, Deal With it!
  • Quotes & Slogans
    • Researchers Reveal the Top 10 Most Effective Safety Slogans Of All Time
    • When Slogans Don’t Work
    • 77 OF THE MOST CLASSIC, FAMOUS and INFAMOUS SAFETY QUOTES
    • 500 BEST WORKPLACE HEALTH and SAFETY SLOGANS 2020
    • 167 CATCHY and FUNNY SAFETY SLOGANS FOR THE WORKPLACE
    • COVID-19 (Coronavirus) Health and Safety Slogans and Quotes for the Workplace
    • Safety Acronyms
    • You know Where You Can Stick Your Safety Slogans
    • Sayings, Slogans, Aphorisms and the Discourse of Simple
    • Spanish Safety Slogans – Consignas de seguridad
    • Safety Slogans List
    • Road Safety Slogans
    • How to write your own safety slogans
    • Why Are Safety Slogans Important
    • Safety Slogans Don’t Save Lives
    • 40 Free Safety Slogans For the Workplace
    • Safety Slogans for Work

Work Method Statement Development Guide

July 19, 2015 by Admin Leave a Comment

imageOh dear……. this guide may excite some safety people and have given the developers a warm fuzzy feeling but it’s missing some crucial components – can you tell me what they are?

Download the Guide Here Work Method Statement Guide

Its pretty obvious what’s missing but there are some clues in these articles if you are unsure:

  • Risk is About People, not just Objects

  • The Arse-Covering Myth

  • Swimming Up Stream and the SWMS Dilemma

  • PASS ME ANOTHER SWMS LEO, THE LAST ONE WAS TOO SHORT

Download the Guide Here Work Method Statement Guide

Work Method Statement Development Guide

for RISK/SAFETY MANAGEMENT SUPPORT REQUIREMENTS

General

A Work Method Statements (WMS) does what?

  • Describes execution of work activity identified within a Scope of Work (otherwise typically known as Standard Operating Procedures of Construction Execution Procedures)
  • Details Work Methodology where Construction and / or Operational Management require a detailed explanation of the required safe system of work – reflected following Risk Assessment and recorded in the Risk Register of the entity controlling the works;
  • Specified by OSH Regulations as a requirement of the entity controlling the works;

Overview of the Work Scope (the Mission)

Describes the scope & work location (MISSION OBJECTIVES & RECEIVING ENVIRONMENT) in enough detail for the work team to understand clearly details of the receiving environment:

§ Location/topography/geology, weather, interfaces

  • § Work site plan / layout drawing attachment that addresses:Exclusion zone/barricading/signage establishment
  • Traffic flow/control,
  • Laydown areas
  • Routine/emergency access/egress
  • Muster/emergency equipment & amenities locations.

Describes the proposed schedule for mobilisation/demobilisation and phases of work flow:

  • Operational/Construction timeline
  • sequence of activities

Considerations in schedule for:

  • Shift work/working hours
  • Work at night (including post-dusk / pre-dawn) and associated logistics e.g. Night Shift/Lighting Plans

Details of Proposed Personnel & Job Positions

§ Work Scope Control/Organisation Flow Chart

  • Discipline Responsibility/Authority Delegation
  • Chain of Command
  • Reporting/Interface Communications between interested parties

In a supporting table format identify :

§ Overview numbers of personnel demonstrating:

  • Task level disciplines/competencies required
  • Unique Training (e.g. VOC or Challenge Testing)
  • Manpower availability & adequacy (Manning histogram) for completion of the tasks in sequence

Detailed description of Work Methodology

§ One work method statement V’s One phase of work or One discipline as required

§ Listed task activities follow logical sequence

§ Task Activities detail a comprehensive, easy to understand, step by step methodology being the basis the job steps listed in the first column of a JHA.

  • Test for Assumption
  • Command language
  • Clear delegation of accountability where possible

Listing of Identified Plant and Equipment required to complete the Scope of Works

In table format identify :

§ Major Plant and Equipment to be mobilised to complete the work described (in particular any plant / equipment either deemed by Statutory Authorities or generally by the entity to be hazardous / high risk).

§ Specific barricading materials/ signage (Type/Quantity)

§ Extra ordinary safety equipment; first aid, emergency, environment, lighting and communications equipment.

§ Availability of arrangements for Ablution, Crib/Welfare, Shelter resources required

Listing of Equipment required should include unique Personal Protective Equipment

§ Identifies the specific (not generic) Personal

Protective Equipment required for the work (eg: Kevlar gloves – not “gloves”)

§ Appropriate for the potential hazards and risks identified.

§ Quantities as part of equipment listing

§ Provide a reference to an attachment or appendices of the WMS confirming that a HazID Workshop was conducted for the scope of work & a listing of all hazards, specific controls unique to the work scope has been established against residual risk scores confirming a Safe System of Work exists prior to mobilizing

§ HazID Worksheets appended to the back of the WMS to reinforce the requirements for Personnel/Competence, Plant/Equipment and procedural inclusions in the previously detailed Work Methodology confirming the establishment of a Safe System of Work.

§ Specific Emergency Response and Rescue planning requirements for the work.

§ Reference to the relevant work activity location specific Emergency Response Planning:

  • Local emergency response contact details (i.e. phone and radio channel)
  • First Aid/Fire response/Mustering
  • Height rescue planning
  • Confined space rescue planning

§ Incorporate into site plan/layout drawing appended to the WMS or provided as an independent supporting documentation.

Environmental Management Requirements

Provide specific detail of any local environmental impact or interface potential and proposed control

  • Environmental uniqueness recognition
  • Chemical transfer methods / location for storage
  • Spill prevention/response (containment, clean up and disposal).
  • Disposal of all hazardous materials / substances strategy
  • Waste Stream management

Details of Hazardous Materials Inventory

Involved Work Activity

§ Identify by name and quantity all Chemicals / Hazardous Materials and Substances (Table Format/Project Approved), safe use associated with the work in accordance with the requirements of the products Material Safety Data Sheets (MSDS).

  • Exposure Monitoring
  • Transfer methods / location for storage
  • Spill prevention/response (containment, clean up and disposal).
  • Disposal of all hazardous materials / substances strategy

§ Copies of MSDS information should be attached to the WMS or listed as contained in the Work Pack

Change Management

§ Identify the necessary activities / processes / documentation required to manage change to the work, location, conditions, or engineering.

  • Relates to Org Chart for approval of change to the signed- off WMS
  • Any Permit To Work requirements for the activity
  • Any Subsequent Risk workshop activity for changes to phases in work scope activity

§ Specify communication methodology to the work force and affected parties:

  • Site Notices
  • Schedule of planned briefings, meetings(SIMOP/SIMCON) /handover sessions
  • ˉTask specific orientation/training sessions.

Forecast Simultaneous Operation Management

& Planning

§ List and known / potential incompatible activities and details of 3rd parties that require a more significant level of

interface management.

  • Shared work location
  • Competing scopes of work same work location
  • Access approval to 3rd Party controlled environments

§ Specify planned representative delegation & involvement and attendance at SIMOP/SIMCON meetings/briefings.

§ Designate delegation of responsibility and relevant Permit system as a control if required to be implemented

Listing of Legislative Reference & Industry

Guidance Material

§ Listing of any specific statutory / regulatory requirements:

  • Australian / New Zealand Standards
  • Codes of Practice
  • Industry guidelines etc relevant to the work.

§ All work as described complies with the relevant sections of:

  • Occupational Safety and Health Act (WA)
  • Occupational Safety and Health Regulations (WA)

Documents listed above should be available for work Team reference if required but are not required to be available in Work Pack

List any applicable HESQ Documents and Plans

§ Any key entity, client or Operational/Project specific HESQ Documentation (Policies, Plans, Procedures, Processes, Forms etc) relevant to the work activity is listed.

Documents listed should be available In Supervisor Work Packs

Applicable Reference Documents & Drawings

§ Lists applicable documentation relevant to the work activity to be readily / easily available at the specific work location:

  • Procedures
  • Specifications
  • Plans (ITP’s, Controls etc)
  • Drawings / diagrams (e.g. P&ID’s, GA’s etc)
  • Lift Studies

Documents listed should be available In Supervisor Work Packs

WMS relationship to Job Hazard Analysis

§ Specifies the allocation of Job Hazard Analysis to a responsible person and the work team/crew undertaking the work.

§ JHA job steps are based on the WMS documented procedural steps.

§ Nominated Supervisory person responsible for work activity should be accountable for ensuring no work commences without a current WMS and JHA review consistent with content of approved WMS

Please share our posts

  • Click to print (Opens in new window)
  • Click to email this to a friend (Opens in new window)
  • Click to share on LinkedIn (Opens in new window)
  • Click to share on Twitter (Opens in new window)
  • Click to share on Telegram (Opens in new window)
  • Click to share on Facebook (Opens in new window)
  • Click to share on Pinterest (Opens in new window)
  • Click to share on Reddit (Opens in new window)
  • Click to share on WhatsApp (Opens in new window)

Related

Filed Under: Work Method Statements Tagged With: Work Method Statements

Reader Interactions

Do you have any thoughts? Please share them below Cancel reply

Primary Sidebar

How we pay for the high cost of running of this site – try it for free on your site

Visit Count – Started Jan 2015

  • 21,279,005 Visitors

Never miss a post - Subscribe via Email

Enter your email address and join over 30,000 other discerning safety people who receive notifications of new posts by email

Please take our 2 minute zero survey

Recent Comments

  • Rob Long on Measurement Anxiety in Safety
  • Antony on Measurement Anxiety in Safety
  • Rob Long on The Quantitative and Qualitative Divide in Safety
  • Bernard Corden on The Quantitative and Qualitative Divide in Safety
  • Bernard Corden on Are You a Safety Clown?
  • Atharva on Road Safety Slogans
  • Rob Long on It’s Always About Paperwork
  • Keith on It’s Always About Paperwork
  • Sairam on Road Safety Slogans
  • Rob Long on Merry Covid Xmas–2020

FREE eBOOK DOWNLOADS

Featured Downloads

  • Public-Event-Risk-Management-Checklist-HD.doc (2367 downloads)
  • violence_checklist.pdf (724 downloads)
  • Amusement Devices Risk Assessment (1015 downloads)
  • ABCs Of Heavy Lifting (4361 downloads)
  • Convention-Flyer-November-2018.pdf (336 downloads)
  • My_Defining Moments in Safety .pdf (2073 downloads)
  • Zero-to-HRO-15-March-2017 (1529 downloads)
  • Broader-Management-Skills.docx (3140 downloads)
  • Falls-Risk-Assessment-Tool.pdf (1871 downloads)
  • Achieve A Safe Workplace (4115 downloads)
  • Risk-Homeostasis-Target-Risk-3.pdf (1877 downloads)
  • Manual Handling Risk Assessment Form (357 downloads)
  • How To Make Your Own Cloth Face Mask (187179 downloads)
  • Parking Lot Safety Moment (8102 downloads)
  • The-air-that-I-breathe.docx (145 downloads)

Recent Posts

  • The Seduction of Slogans in Safety
  • Certificate, Diploma and Masters Studies in SPoR
  • Measurement Anxiety in Safety
  • Are You a Safety Clown?
  • The Quantitative and Qualitative Divide in Safety
  • Balance in Risk and Safety
  • It’s Always About Paperwork
  • Sin-Eaters for Safety
  • Mixed Messages but No Redemption
  • The Silver Bullet

Footer

AUTHORS

  • Alan Quilley
    • Heinrich–Industrial Accident Prevention
    • The Problem With ZERO Goals and Results
  • Bernard Corden
    • AHH$ Covid$afe Chri$tma$ New$letter
    • Paradise by the dashboard light
  • Bill Sims
    • Employee Engagement: Chocolate, Vanilla, or Strawberry?
    • Injury Hiding-How do you stop it?
  • Craig Clancy
    • Task Based vs Activity Based Safe Work Method Statements
    • Safety And Tender Submissions
  • Daniel Kirk
    • It’s easy being wise after the event.
    • A Positive Safety Story
  • Dave Whitefield
    • Safety is about…
    • Safety and Compliance
  • Dennis Millard
    • Are You Risk Intelligent?
    • Honey they get me! They get me at work!
  • Drewie
    • Downturn Doin’ Your Head In? Let’s Chat….
    • How was your break?
  • Gabrielle Carlton
    • All Care and No Care!
    • You Are Not Alone!
  • George Robotham
    • How to Give an Unforgettable Safety Presentation
    • How To Write a Safety Report
  • Goran Prvulovic
    • Safety Manager – an Ultimate Scapegoat
    • HSE Performance – Back to Basics
  • James Ellis
    • In search of plan B in workers’ recovery
    • What and how should we measure to support recovery from injury?
  • James Parkinson
    • To laugh or not to laugh
    • People and Safety
  • John Toomey
    • Who is Responsible for This?
    • Who Are Your People?
  • Karl Cameron
    • Abby Normal Safety
    • The Right Thing
  • Ken Roberts
    • Safety Legislation Is Our Biggest Accident?
    • HSE Trip Down Memory Lane
  • Mark Perrett
    • Psychology of Persuasion: Top 5 influencing skills for getting what you want
  • Mark Taylor
    • Build a Psychologically Safe Workplace by Taking Risks and Analysing Failures
    • Enculturing Safety
  • Max Geyer
    • WHS Legislation is NOT about Safety it’s about Culture
    • Due Diligence Is Not Just Ticking Boxes!
  • Matt Thorne
    • It was the SIA until someone wanted to swing from the Chandelier
    • Common Sense is Remarkably Uncommon
  • Peter Ribbe
    • Is there “Common Sense” in safety?
    • Who wants to be a safety professional?
  • Phil LaDuke
    • Hey Idiots, You’re Worried About the Wrong Things
    • Misleading Indicators
  • Admin
    • Certificate, Diploma and Masters Studies in SPoR
    • Merry Covid Xmas–2020
  • Dr Rob Long
    • The Seduction of Slogans in Safety
    • Measurement Anxiety in Safety
  • Rob Sams
    • I’m just not that into safety anymore
    • Social ‘Resiliencing’
  • Barry Spud
    • Barry Spud’s Hazard Control Tips
    • Researchers Reveal the Top 10 Most Effective Safety Slogans Of All Time
  • Sheri Suckling
    • How Can I Get the Boss to Listen?
  • Safety Nerd
    • The Block isn’t portraying safety as it should be
    • Toolbox Talk Show–PPE
  • Wynand Serfontein
    • Why The Problem With Learning Is Unlearning
    • I DON’T KNOW
  • Zoe Koskinas
    • Why is fallibility so challenging in the workplace?

FEATURED POSTS

Investigations and Truth Telling

The Illusion Of Hazard Identification

A Conference with a Difference

I am a Spreadsheet King

An Engineering Dreamworld

Banning Head Protection is Safer

Compliance, Obedience and The Attraction of Risk

Doing Something Bad Well

In Praise of In-Between Thinking in Risk and Safety

Safety Holistically a Case for Change

Envisioning and Creativity in Safety

Safety for Luddites

Zero Suicide and the Discourse of Denial

Stop the Train I Want to Get Off

The Immediacy of Zero

Framing Your World

Culture About Much More Than Structure

The Convenience of Complacency

Words Can Change Your Brain

Semiotics and Unconscious Communication in Safety

More Posts from this Category

Paperwork

https://vimeo.com/162034157?loop=0

Due Diligence

https://vimeo.com/162493843?loop=0

loading Cancel
Post was not sent - check your email addresses!
Email check failed, please try again
Sorry, your blog cannot share posts by email.